Warehouse Unit, Stoke On Trent - New Build Full SIte
Posted on 29th November 2022 at 12:00
Site: Unit C250 Stoke Central Industrial Estate
Location: Stoke On Trent
Type of Works: New Build/Base Build Fit-Out
Duration: 20 Weeks
Electrical Value: £700k
ECO2LEC carried out the full electrical design of a 250k sqft prospective build warehouse unit.
Final electrical installation on the site consisted of:
Ground Floor: Reception Feature Wall Lighting, Kitchenette And Accessible Shower Room/Toilet.
First Floor: Circulation Area, Accessible Shower Room, Escape Stair.
Second Floor: Circulation Area, Accessible Shower Room, Escape Stair.
Roof Access Lighting.
Hub Office Circulation Area Lighting And Power.
ECO2LEC installed the following services;
HV electrical installation. Internal intelligent Bluetooth controlled LED lighting with daylight dimming to the reception area and occupancy sensored fittings to the toilets and circulation spaces.
Small power installations to kitchenette, reception and circulation spaces.
L1 fire detection systems to the circulation spaces.
Disabled refuge system.
Emergency lighting provisions to the circulation spaces.
Dock leveller supplies.
Building mounted external lighting covering the full perimeter of the buildings.
Loading yard & car park lighting.
EV Chargers throughout the carpark.
HV Electrical Installation
LV Electrical Distribution
Intelligent Bluetooth LED Lighting Complete With Daylight Dimming
Perimeter External Lighting
Loading Bay Lighting
Loading Yard Lighting
Car Park Lighting
Mechanical supplies
Dock Leveller Supplies
Cat L1 Fire Alarm Installation (Office Core)
Disabled Refuge
Accessible Toilet Alarms
24 Dual Electric Vehicle Charging Pedestals Complete With Load Management
Additional Client Requested External & Internal Supplies