CML 3, Lutterworth - Mezzanine Fit-Out
Posted on 21st February 2017 at 12:00
Site: CML 3, Mezzanine Fit-Out
Location: Magna Park, Lutterworth
Type of Works: Industrial/Fit-Out
Duration: 10 Weeks
Electrical Value: £200K
Phase 1 consisted of relocating the existing and the installation of additional high bay lighting to suit the new racking layouts. Phase 2 consisted of the full electrical fit out of a picking mezzanine over 3 floors. The installation included 700 LED vapour proof light fittings installed upon over 2KM of Zucchini Lighting Busbar, small power & data, conveyor supplies & control wiring, emergency lighting and fire detection all delivered on time and within budget.
Over 700 PIR Controlled LED Lights
Over 2 KM Lighting Busbar Installed
Fire Alarm Installation
Data Installation
Machine Supplies
All carried out without disruption to operations!