Baden Place, Central London - Office Refurbishment
Posted on 21st February 2017 at 12:00
Site: Baden Place Crosby Row, Office Refurbishment
Location: Southwark, Central London
Type of Works: Commercial/Refurbishment
Duration: 26 Weeks
Electrical Value: £250K
ECO2LEC LTD were tasked with the strip-out and reinstatement of five office units in the heart of London. Over a span of 26 weeks the units were stripped to a bare shell and exposed containment systems installed to give an industrial finish. Lighting design carried out in house, the LED suspended panels offer a uniform finish throughout the units. Each office also contained a kitchenette with electric water heater and toilet blocks with extract and hand dryers.
Full office refurbishments including; small power, lighting, data and fire alarm.
Communal lighting and toilet area refurbishments.
LED Lighting
Metal Clad Accessories
Galvanised Containment Systems
Fire Alarm Installation
Data Installation
Mechanical Supplies
Tagged as: Commercial, Office Refurbishment